Thalpitigala Reservoir Project

Thalpitigala Reservoir Project

Client:
Ministry of Irrigation
Location:
Sri Lanka / Badulla
Scheduled:
2019 -2023
Services:
Design & Supervision
Project Value:
LKR 395 Mn

Thalpitigala Reservoir of 15.56 MCM capacity by constructing a 280 m long and 45.7 m high roller Compacted Concrete (RCC) dam across the Uma Oya and diverting the stored water to the Power house through a 1.455 km long 3.5 m diameter headrace unlined tunnel to generate 51.3 GWh of power annually by two 7.5 MW turbines. Exit water of the power house will then be sent to the Bathmadilla anicut for the purpose of irrigation requirements.