Client: | Mahaweli Authority of Sri Lanka |
Location: | Kotmale |
Completed: | 1980 -1984 |
Services: | Design & Supervision |
Description:
The project comprised construction of a 87m high rock fill dam with upstream concrete membrane, having a crest length of 600 m, and radial gated chute type spillways. The concrete lined power tunnel is 6.8 km long. Installed capacity is 2 X 67 MW with provision for a third unit of 67 MW.